Nvidia Commits $105B Financing and $1.5B Equity for OpenAI's Ohio Data Center at PORTS-Pike Campus

MarketsTop News20 sources·Aug 16

Summary

Updated Aug 17 — Nvidia officially committed $105B in credit and $1.5B equity to SB Energy for OpenAI's Ohio data center, confirmed via SEC filing.

  • • Nvidia officially committed $105 billion in credit financing and a $1.5 billion equity stake in SB Energy for OpenAI's data center at PORTS-Pike Technology Campus in Pike County, Ohio, disclosed via SEC filing.
  • • The facility, built and managed by SB Energy under a 20-year lease to OpenAI, will scale from 4.25 GW to 8 GW of compute capacity in phases from 2028; Nvidia is the exclusive compute supplier.
  • • SB Energy will build a 9.2 GW natural gas power plant on a former DoE uranium enrichment site to power the campus, at an estimated cost of ~$33 billion.
  • • The $105B figure represents the finalized deal terms — down from earlier CNBC-reported $250B discussions and WSJ's estimate of less than $120B.
Adjust signal

Updates

Aug 18
Financials

Nvidia invested $30B directly in OpenAI equity (February 2026)

In February 2026, Nvidia separately invested $30 billion directly in OpenAI — in addition to the $105B credit backstop for SB Energy and the $1.5B SB Energy equity stake. OpenAI relies on Vera Rubin, Nvidia's most advanced compute system, for training capacity.

Strategy

Jensen Huang: AI labs 'growing faster than their balance sheets'

Nvidia CEO Jensen Huang posted on X: 'Frontier AI labs have extraordinary demand for training and inference compute, but many are growing faster than their balance sheets and long-term credit profiles can support. They may have strong customer demand and rapidly growing revenue yet still lack the decades-long infrastructure contracts and investment-grade financing capacity needed to secure the AI factory infrastructure independently.'

Market Impact

Cantor: deal signals 'elongated and durable' AI investment cycle

Cantor analysts reiterated a buy rating on Nvidia and wrote that the deal is 'a clear signal that the current AI investment cycle will be elongated and durable.' They described Nvidia's capital deployment as 'less circular and more facilitating the coming AI buildout while creating additional competitive moats.'

Financials

Nvidia FCF $48.5B; equity holdings $30.2B; $80B buyback

Nvidia's quarterly free cash flow reached $48.5 billion in the latest period — up 18-fold over three years, following 12 consecutive quarters of revenue growth above 55%. The company holds $30.2 billion in marketable equity securities (up from $12.9B a year earlier) and in May 2026 announced an $80 billion stock buyback and raised its quarterly dividend to 25 cents per share.

Strategy

$500B Wall Street GPU financing pact announced week prior

One week before the Ohio data center commitment, Nvidia announced a memorandum with leading Wall Street firms to pursue $500 billion in financing for Nvidia GPUs — positioning Nvidia hardware as a financeable asset class. Jensen Huang made the announcement alongside six Wall Street financiers at CNBC.

Aug 17
Financials

$105B credit financing confirmed via SEC filingrevised

Official SEC disclosure confirms Nvidia will provide up to $105 billion in credit to SB Energy for the Ohio data center buildout — the finalized figure, revised down from earlier CNBC-reported $250B backstop discussions and WSJ's estimate of less than $120B. Earlier reporting had indicated approximately $100B.

Financials

$1.5B Nvidia equity stake in SB Energy

Nvidia will invest $1.5 billion directly in SB Energy, securing its role as the exclusive compute supplier at the Ports-Pike data center. SoftBank and OpenAI are existing SB Energy investors; SoftBank had previously held $5.8 billion in Nvidia stock, sold in November 2025.

Infrastructure

4.25 GW initial → 8 GW total; 20-year OpenAI lease starting 2028

The facility will begin at 4.25 GW of compute capacity with an option to expand by an additional 3.75 GW, for a potential 8 GW total. OpenAI holds a 20-year lease; capacity is expected to come online in phases starting in 2028.

Infrastructure

$33B natural gas power plant on former DoE nuclear site

SB Energy will build a 9.2 GW natural gas power plant at the PORTS-Pike campus, estimated at approximately $33 billion in cost — reflecting a 66% rise in natural gas plant costs over the past two years. The site previously enriched uranium for the U.S. nuclear arsenal and Navy submarines.

Context

PORTS-Pike campus, Pike County, Ohio; Sam Altman early SB Energy investor

The data center is located at the PORTS-Pike Technology Campus in Pike County, Ohio. Sam Altman was an early personal investor in SB Energy. SoftBank and OpenAI are existing SB Energy investors.

Stat

35,000 construction jobs; 2,500 long-term positions by 2032

OpenAI said the PORTS-Pike data center project will support approximately 35,000 new construction jobs through 2032 and 2,500 long-term operational positions at the campus.

Context

Greg Brockman: compute is 'the new oil'

OpenAI president Greg Brockman told CNBC's Squawk Box: 'Compute is really becoming the new oil, the new limited resource of the AI age.' Brockman described compute as a 'fundamental resource' for the entire AI industry.

Details

Financials

Nvidia nearing deal to guarantee ~$100B in OpenAI data center financing

The deal would have Nvidia guarantee or provide approximately $100 billion in credit/financing support for OpenAI's data center infrastructure buildout.

Strategy

Deal structured as financing guarantee, not direct equity investment

The current arrangement differs from the original equity-style investment; Nvidia may also invest up to $3B in related entities separately.

Infrastructure

Partnership targets deployment of at least 10 gigawatts of Nvidia compute

Under the original MOU framework, OpenAI would lease Nvidia systems at a scale of at least 10 gigawatts of computing power.

Infrastructure

Deal reportedly tied to large Ohio data center project with SB Energy

Reports indicate the financing is linked to a large-scale data center buildout potentially involving an Ohio facility and clean energy partner SB Energy.

Context

Original Nvidia-OpenAI MOU was announced September 22, 2025

The original strategic partnership announced in Sept. 2025 called for Nvidia to invest up to $100B progressively as each gigawatt of compute was deployed.

Context

WSJ reported the deal stalled in January 2026 amid Nvidia doubts

CEO Jensen Huang privately downplayed the original deal; reports indicated a possible shift toward a smaller ~$30B equity investment before the current revival.

Market Impact

Deal cements Nvidia as OpenAI's primary infrastructure partner at IPO scale

Locking in OpenAI as a 10GW customer reinforces Nvidia's hardware dominance ahead of OpenAI's anticipated multi-trillion-dollar IPO valuation.

Other

Details compiled via Grok live web research from The Information and other outlets

Primary article was a tweet-only source; details sourced from The Information, WSJ, NVIDIA Newsroom, and NYT via Grok live research.

Deal structure, scale, history, and strategic implications of Nvidia's financing guarantee for OpenAI data centers.

What This Means

The official disclosure of Nvidia's $105 billion credit commitment and $1.5 billion equity stake in SB Energy confirms one of the most consequential AI infrastructure deals ever recorded — moving from months of speculation to SEC-filed reality. The deal cements Nvidia as OpenAI's exclusive compute supplier at the PORTS-Pike Ohio campus, formalizing the strategic alliance at a figure that has narrowed significantly from initial $250 billion reports. The 9.2 GW natural gas power plant — built on a former nuclear weapons site and estimated at $33 billion — illustrates the extraordinary physical and energy infrastructure being assembled to support AI's commercial boom. OpenAI president Greg Brockman's characterization of compute as 'the new oil' captures the strategic stakes: access to scarce, high-performance compute has become the primary bottleneck for AI progress and competitive positioning, and this deal locks in one of the world's most powerful supply chains for decades.

Sentiment

Mostly neutral reporting with investor scrutiny on financing scale and risks

@amirAmir Efrati · Executive Editor @theinformationView post
Informative

“AI infrastructure news: Nvidia previously discussed $250 billion financial backstop for OpenAI / Softbank Energy mega site in Ohio, which spooked investors, but… financial guarantee being discussed rn is actually ~$100B. Still a lot!”

@validapauValida Pau · Reporter @theinformation covering tech M&A and IPOsView post
Informative

“NEW: Nvidia is close to a deal to guarantee ~$100 billion in credit support for OpenAI to lease a proposed AI data center campus in Ohio.”

@MikeZaccardiMike Zaccardi, CFA, CMT · Financial writer. Markets & chartsView post
Informative

“WSJ: Nvidia scales back OpenAI data-center guarantee to less than $120B”

@pstAsiatechPaul Triolo · Partner, China/Tech Policy Lead DGA ASG; ASPI CCAView post
Informative

“Nvidia Close to Deal to Guarantee About $100 Billion in Credit for OpenAI”

@PankajInsightsPankaj Kumar · Equity Research | AI EnthusiastView post
Skeptical

“Nvidia ($NVDA) cuts its OpenAI Ohio data center guarantee by more than half (to <$120B from $250B). It is trying to address investors anxiety around circular financing risks without backing off the world's largest 10 GW AI infrastructure build-out.”

Split

~80/20 neutral-to-skeptical (most sharing news; minority flags circular financing/investor anxiety risks).

Sources

Update history (3)
Aug 20Added Grok Sweep article as corroborating source; covers the earlier '$250B → <$120B' reduction phase already captured in the event's confirmed $105B SEC filing record.
Aug 18Added CNBC analysis with Jensen Huang's X post quote, Cantor buy-rating note, Nvidia's previously unreported $30B direct equity investment in OpenAI (February 2026), and supporting financial metrics (FCF, equity securities, $80B buyback, $500B Wall Street GPU financing pact).
Aug 17Nvidia officially committed $105B in credit and $1.5B equity to SB Energy for OpenAI's Ohio data center, confirmed via SEC filing.Deal officially disclosed via SEC filing: updated title and tier1_scan to reflect finalized terms; added 7 rows covering $105B credit confirmation, $1.5B equity in SB Energy, facility specs (4.25→8 GW), $33B natural gas power plant on former DoE nuclear site, job projections, and Greg Brockman 'new oil' quote.